肥槽回填对装配式地下车站结构的力学影响 被引量:1

Mechanical Influences of Foundation Trench Backfillingon Prefabricated Underground Station Structure
下载PDF
导出
摘要 肥槽回填是明挖装配式地下车站的主要施工阶段,对装配式地下结构的内力和变形有重要影响。针对肥槽回填阶段装配式地下车站结构的力学特性,建立增量法结构计算模型,对不同肥槽的回填材料、回填方案以及中板结构施作的先后次序等工况下的装配式地下车站的结构进行分析,研究不同工况对装配式地下车站结构内力和稳定性的影响。研究结果表明:①采用常规土体材料进行肥槽回填,其回填荷载会导致该阶段装配式结构部分的接头内力超过接头承载能力,回填荷载作用下结构有失稳趋势(拱脚支撑受拉);②采用结硬性材料进行肥槽回填,不同分层方式的回填方案对装配式结构的接头内力和稳定性影响差异较大,其中结硬性回填材料一次性回填对结构的影响比常规土体回填更大,分多层回填时能有效降低回填荷载的影响,采用4次分层回填方案,结构受力与变形均有大幅改善,能确保结构稳定性,使接头承载性能满足要求;③在肥槽回填之前施工中板结构,能大幅改善肥槽回填荷载对结构接头承载能力和稳定性的影响,各种回填方案均能满足结构受力和稳定性的要求,因此中板施工前置工况可降低对肥槽回填材料和方案的要求,不排除今后采用较低强度结硬性材料回填的可能性。 Backfilling a foundation trench is the main stage in the construction of an open-excavation prefabricated underground station structure and has a significant influence on the internal force and deformation of the structure.In this study,an incremental method calculation model was established based on the mechanical characteristics of a prefabricated underground station structure during the backfilling stage.The structure under the working conditions of backfill materials,backfill schemes,and orders of construction of the middle-floor structure were analyzed.The effects of different working conditions on the internal structural force and structural stability of the structure were studied.The following results were found.First,using conventional soil material for the backfill of the foundation trench,the backfilling load(arch foot support tension)caused the internal forces of some joints of the prefabricated structure to exceed their bearing capacity,and the structure became unstable.Second,when hardening material was used for backfill and different layered backfill schemes exerted greatly different impacts on the prefabricated structure joint internal force,the structural stability.Among the schemes investigated,the one-time hardening backfill material scheme resulted in a greater structural stability than that of a conventional soil backfill.Multilayer backfilling can effectively reduce the impact of the backfill load,and the use of a four-layered backfill scheme could minimize the stress and deformation of the structure and thus ensured the stability of the structure,and the bearing performance of the joint met the requirements.Third,when the floor structure was constructed before backfilling,the influence of the backfilling load on the bearing capacity of the structural joint and the structural stability were greatly improved.All types of backfilling schemes met the requirements of structural force and stability,suggesting that the pre-construction conditions of the floor have lower requirements for backfilling materials and schemes.The possibility of backfilling with a low-strength bonded material cannot be ruled out.
作者 彭智勇 杨秀仁 王臣 黄美群 林放 PENG Zhiyong;YANG Xiuren;WANG Chen;HUANG Meiqun;LIN Fang(National Engineering Research Center for Green and Safe Construction Technology in Urban Rail Transit,Beijing 100037;Beijing Urban Construction Design and Development Group Co.Ltd.,Beijing 100037)
出处 《都市快轨交通》 北大核心 2023年第2期100-106,126,共8页 Urban Rapid Rail Transit
基金 国家重点研发计划(2017YFB1201104) 北京城建集团创新项目(CJJT2022-002)。
关键词 地铁 肥槽回填 明挖预制装配式地下车站结构 结硬性回填 增量法计算 metro foundation trench backfill open-cut prefabricated underground station structure hardening material backfill structural calculations
  • 相关文献

参考文献8

二级参考文献27

  • 1杨秀仁,黄美群,林放.地铁车站预制装配式结构注浆式榫槽接头弯曲抵抗作用特性研究[J].土木工程学报,2020,53(2):33-40. 被引量:40
  • 2张承志.试体尺寸对碱集料反应膨胀的影响.第四届北京国际水泥与混凝土会议论文集,卷1[M].北京,1998.334.
  • 3GB50157-2003地铁设计规范[S].北京:中国计划出版社,2003.
  • 4GB50010-2010,混凝土结构设计规范[s].北京:中国建筑工业出版社.2010.
  • 5JGJ120-99建筑基坑支护技术规程[S].北京:中国建筑工业出版社,1999
  • 6YB9258-97建筑基坑工程技术规范[S].北京:冶金工业出版社,1997.17-26.
  • 7北京城建设计研究总院有限责任公司.合肥市轨道交通1号线大东门站初步设计图C版[G],北京,2012.
  • 8北京城建勘测设计研究院有限责任公司.合肥市轨道交通1号线一期工程大东门站岩土工程勘察报告[R].北京,2010.
  • 9朱海良,严炳舵.双圆隧道管片制作技术[J].地下工程与隧道,2008(1):38-42. 被引量:1
  • 10张弛.法国大跨度隧道预制管片装配法施工技术[J].世界隧道,1997(2):10-18. 被引量:8

共引文献120

同被引文献13

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部