肥田煤矿综采工作面设备回收工艺运用 被引量:1

Application of Equipment Recovery Technology in Fully Mechanized Mining Face of Feitian Coal Mine
下载PDF
导出
摘要 为研究综采工作面开采后设备回收流程及工艺运用,以肥田煤矿111601综采工作面为背景,分析了设备的回收流程及回收过程中相关设备的参数选择。针对矿井实际情况制定了科学准确的回收方案,确定由运输顺槽与回风顺槽2条路线运出综采设备;通过理论计算与现场实测的方式确定了绞车牵引液压支架个数,并在回收过程中对顶板、瓦斯进行规范管理;针对采面不同顶板条件设计了不同的顶板支护方案,总结出了回收过程中的安全技术。 In order to study the equipment recovery process and process application after mining in ful ly mechanized mining face,taking 111601 fully mechanized mining face of Feitian Coal Mine as the back ground,the equipment recovery process and the parameter selection of related equipment in the recovery process are analyzed.According to the actual situation of the mine,a scientific and accurate recovery scheme was formulated,and the fully mechanized mining equipment was determined to be transported from the two routes of the transportation gateway and the return air gateway.Through theoretical calculation and field measurement,the number of winch traction hydraulic support is determined,and the roof and gas are standardized in the recovery process.Different roof support schemes are designed for different roof condi tions of the mining face,and the safety technology in the recovery process is summarized.
作者 尚金海 SHANG Jinhai(Feitian Coal Mine,Zhongcheng Energy Co.,Ltd.)
出处 《现代矿业》 CAS 2023年第4期59-61,65,共4页 Modern Mining
关键词 综采工作面 设备回收 绞车牵引 顶板管理 comprehensive working face equipment recovery winch traction roof control
  • 相关文献

参考文献5

二级参考文献53

共引文献74

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部