以江西某隧道项目为例,通过对其Ⅴ级围岩的周边收敛及拱顶、地表沉降数据进行处理、回归分析及对比,有效提高现场施工数据的准确性,优化施工设计,保证施工安全。
As an example in a tunnel in Jiangxi,through the processing,regression analysis and comparison of surrounding convergence and settlement data of vault and surface of grade V surrounding rock,it can effectively improve the accuracy of construction site data,optimize the construction design and ensure the construction safety.
作者
周文兵
陈秋南
唐勇
ZHOU Wen-bing;CHEN Qiu-nan;TANG Yong(School of Civil Engineering,Hunan University of Science and Technology,Xiangtan,Hunan,411201,China)
出处
《建材技术与应用》
2023年第3期46-50,共5页
Research and Application of Building Materials
关键词
隧道工程
监控量测
新奥法
回归分析
tunnel engineering
monitoring measurement
New Austrian Tunnelling Method(NATM)