海水循环泵顶盖泥沙淤积问题分析及应对措施研究

Study on Analysis and Countermeasures for Sediment Deposition on TopCover of Seawater Circulation Pump
下载PDF
导出
摘要 秦山二期海水循环泵运行过程中,经常由于盘根严重磨损,出现轴封处海水泄漏现象。海水泄漏造成顶盖处泥沙淤积,导致顶盖排水泵频繁故障,曾引发海水循环泵下部油箱进水,严重影响循环水泵运行可靠性。对顶盖泥沙淤积的原因及危害进行剖析,找到相应解决方法,并针对目前依旧存在的问题寻求更完善的解决方案。 During the operation of Qinshan Phase II seawater circulating pump,seawater leakage at the shaft seal is often caused by serious wear of packing roots.Seawater leakage caused sediment deposition on the top cover,resulting in frequent failure of the top cover drainage pump,which once caused water inflow into the lower oil tank of the seawater circulating pump,seriously affecting the operation reliability of the circulating pump.The causes and hazards of siltation on top cover are analyzed,corresponding solutions are found,and more perfect solutions are sought for the existing problems.
作者 王小闯 董俊斌 WANG Xiaochuang;DONG Junbin(CNNP Nuclear Power Operations Management Co.,Ltd.,Jiaxing 314300,China)
出处 《电工技术》 2023年第8期202-204,共3页 Electric Engineering
关键词 海水循环泵 泥沙淤积 盘根泄漏 轴封供水 seawater circulating pump sediment deposition packing leakage shaft seal water supply
  • 相关文献

参考文献5

二级参考文献22

共引文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部