摘要 针对装配式预制构件连接部位受力特点、安装控制难点及套筒加工工艺、原材料、成本等问题,基于冷锻压和热处理工艺,设计新型锻压式半灌浆套筒,按照规范要求制作对中连接试件和偏心连接试件,通过单向拉伸试验对接头连接试件极限承载力、残余变形、最大总伸长率等力学参数以及套筒表面应变分布规律等进行研究分析。结果表明:试件破坏均为连接钢筋拉断破坏,各项参数指标均满足JGJ107—2016Ⅰ级连接接头的相关要求;试件破坏荷载-位移曲线与钢筋原材相似,包含弹性阶段、屈服阶段、强化阶段和连接钢筋颈缩断裂阶段,但试件屈服台阶和强化阶段曲线均较钢筋原材长,灌浆接头可靠性更高;套筒对灌浆料具有主动约束作用,在一定程度上增加灌浆锚固段锻压凹槽数量,有助于提高套筒对灌浆料的轴向滑移约束和径向膨胀开裂约束作用。 In view of the stress characteristics of the connection part of the prefabricated components,the installation control difficulties,the sleeve processing process and the cost of raw materials,a new forging semigrouting sleeve was designed based on cold forging pressing and heat treatment processes.In this paper,the alignment connection specimen and the eccentric connection specimen were prepared according to the specifications.Through the unidirectional tensile test,the ultimate bearing capacity,residual deformation,maximum total elongation and other mechanical parameters of the joint connection specimens and the strain distribution law on the sleeve surface were studied and analyzed.The results showed that the failure modes of the specimens were all tensile failures at non-specific locations of the connecting steel bars,and all the parameters satisfied the requirements for the tensile strength of the joint of I grade in JGJ 107—2016.The failure load-displacement curve of the specimen was similar to the original steel bar,and both included the elastic stage,the yield stage,the strengthening stage and the fracture stage.However,both the yield step and the strengthening curve of the specimen were longer than the original steel bar,so the grouting joint was more reliable.The sleeve had an active restraint effect on the grouting material.To a certain extent,increasing the number of forging grooves in the grouting anchoring section was beneficial to improve the axial slip restriction and radial expansion cracking restraint effect of the sleeve on the grouting material.
作者 郑志涛 杨皓东 徐颖 涂刚要 郝留照 ZHENG Zhitao;YANG Haodong;XU Ying;TU Gangyao;HAO Liuzhao(Postdoctoral Working Station of Hefei Construction Engineering Group Co.,Ltd.,Hefei 230088,China;Postdoctoral Research Station of Anhui University of Science and Technology,Huainan 232001,China;Langfang Yuzeli Building Material Technology Co.,Ltd.,Langfang 065000,China)
出处 《结构工程师》 2023年第2期97-106,共10页 Structural Engineers
基金 安徽省建设厅科技计划项目(2019YF-006)。
关键词 预制构件连接 半灌浆套筒 无缝钢管 力学性能 单向拉伸试验 prefabricated component connection semi-grouting sleeve seamless steel pipe mechanical properties uniaxial tensile test
  • 相关文献

参考文献10

二级参考文献59

  • 1徐有邻,汪洪,沈文都.钢筋搭接传力性能的试验研究[J].建筑结构,1993,23(4):20-24. 被引量:16
  • 2徐芝纶.弹性力学[M].北京:高等教育出版社,2006.
  • 3JGJl07--2010钢筋机械连接技术规程[S].北京:中国建筑工业出版社.2010.
  • 4Splice-sleeve north America [ EB/OL ]. http://www.Splicesleeve. com.
  • 5Einea A, Y amane T,Tadros M K. Grout-filled pipe splices forprecast concrete construction [ J]. PCI Journal,1995,40 ( 1):82-93.
  • 6Yee A A. Structural and economic benefits of precast/prestressedconcrete construction [J]. PCI Journal, 2001,46(4) :34-43.
  • 7郭正兴,郑永峰,刘家彬,等.一种钢筋浆锚对接连接的灌浆变形钢管套筒[P].中国专利:ZL201320407071.4,2014.
  • 8Soleymani Ashtiani M, Dhakal R P, Scott A N. Post-yield bondbehaviour of deformed bars in high-strength self-compactingconcrete [ J ] . Construction and Building Materials, 2013 , 44(7):236-248.
  • 9JGJ107-2010钢筋机械连接技术规程[S].北京:中国建筑工业出版社,2010.
  • 10Untrauer R E, Henry R L. Influence of normal pressure on bondstrength[ C ]//ACI Journal Proceedings. ACI, 1965,62(5):577-586.

共引文献174

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部