城市狭小空间超高层建筑地下室半逆作施工 被引量:1

Semi-inverse Construction of Basement of Super High-rise Building in Narrow Spacein City
下载PDF
导出
摘要 以南宁世贸中心二期项目为例,对施工区域狭小、基坑深度较大、与地铁距离较近的超高层建筑地下室半逆作施工技术进行了研究。针对无法采用预应力锚索支护的基坑,通过采用单排桩+楼板支撑,地下室2层以下采用半逆作法施工,不但安全有效地保证了施工质量,还加快了施工进度。实践证明,该施工技术能有效节约施工成本,社会效益和经济效益明显。 Taking the second phase project of Nanning World Trade Center as an example,this paper studies the semi-inverse construction technology for the basement of super high-rise building with narrow construction area,deep foundation pit and close distance to the subway.For the foundation pit which cannot be supported by prestressed anchor cable,the semi-reverse construction method is used below the second floor of the basement by using singlerow piles and floor support,which not only ensures the construction quality safely and effectively,but also speeds up the construction progress.The practice proves that the construction technology can effectively save the construction cost,the social and economic benefits are obvious.
作者 刘超 王洵诣 LIU Chao;WANG Xunyi(China Railway Tianfeng Construction Engineering Limited Company,Beijing 102308,China)
出处 《建筑施工》 2023年第5期862-864,共3页 Building Construction
关键词 超高层建筑 深基坑 狭小空间:半逆作法 super high-rise building deep foundation pit narrow space semi-inverse construction method
  • 相关文献

参考文献6

二级参考文献20

共引文献88

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部