高速铁路隧道接触网预埋槽道的常见问题及预防事项

Common Problems and Prevention Measures of Pre-buried Channels for Overhead Contact System in High-Speed Railway Tunnels
下载PDF
导出
摘要 隧道接触网预埋槽道是铁路站前土建施工非常重要的一项工作,因槽道预埋位置精度要求高,无法进行返工处理,一旦出现问题就要进行后置,后置预埋槽道的成本高,施工难度大。近年一些铁路项目均出现了槽道预埋不合格,需要后期槽道外置,外置费用高,造成了巨大的经济损失。本文结合某铁路项目隧道工程预埋槽道出现的问题,谈谈典型的错误方式及后期预防方法。 The pre-buried channels for the over head contact system is a crucial task in the civil construction of railway stations.Due to the high precision requirements of the pre-buried channel position,rework is not feasible.Once problems occur,it requires subsequent adjustments,which incur high costs and pose great construction difficulties.In recent years,several railway projects have encountered issues with non-compliant pre-buried channels,leading to the need for external placement and resulting in significant economic losses.This paper discusses the typical mistakes and preventive measures based on the problems encountered in the pre-buried channels of a specific railway tunnel project.
作者 倪派 Ni Pai(China Railway Fifth Bureau Group South China Engineering Co.,Ltd.,Dongguan,Guangdong)
出处 《石家庄铁路职业技术学院学报》 2023年第2期49-52,共4页 Journal of Shijiazhuang Institute of Railway Technology
关键词 隧道 接触网 预埋槽道 预防 tunnel contact system pre-buried channels prevention
  • 相关文献

参考文献2

二级参考文献6

共引文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部