地毯厂生产废水处理站提标改造工程设计与应用 被引量:1

Design and application of upgrading project of production wastewater treatment station in carpet factory
下载PDF
导出
摘要 以河南某地毯厂为例,污水处理规模为100 m^(3)/d,原水化学耗氧量(COD)2500~3200 mg/L、五日生化需氧量(BOD_(5))1000~1500 mg/L、氨氮(NH_(3)-N)30~50 mg/L、总氮(TN)40~70 mg/L、固体悬浮物(SS)400~700 mg/L、色度800~1000倍,在原污水处理工艺的基础上增加缺氧处理工艺和混凝沉淀处理工艺。处理后出水水质满足《河南省黄河流域水污染物排放标准》(DB 41/2087—2021)规定限值,即COD≤40 mg/L、BOD_(5)≤10 mg/L、NH_(3)-N≤3 mg/L、TN≤12 mg/L、SS≤20 mg/L、色度≤30倍。该改造工艺运行费用低、管理简单方便、易于操作、无二次污染。 Taking a carpet factory in Henan as an example,the wastewater treatment capacity is 100 m^(3)/d.The influent COD,BOD_(5),NH_(3)-N,TN,SS,chroma are 2500~3200 mg/L,1000~1500 mg/L,30~50 mg/L,40~70 mg/L,400~700 mg/L and 800~1000 times.On the basis of original wastewater treatment process,the anoxic treatment process and coagulation sedimentation treatment process were added.After treatment,the effluent quality meet and standard stipulated in the Standard for discharge of water pollutants in the Yellow River basin of Henan province(DB 41/2087—2021),such as COD≤40 mg/L,BOD_(5)≤10 mg/L,NH_(3)-N≤3 mg/L,TN≤12 mg/L,SS≤20 mg/L and chroma≤30 times.The transformation process has low operation cost,simple and convenient management,facile operation and no secondary pollution.
作者 逯通 张卓林 王盼明 刘峻 朱亚飞 LU Tong;ZHANG Zhuo-lin;WANG Pan-ming;LIU Jun;ZHU Ya-fei
出处 《节能》 2023年第5期87-89,共3页 Energy Conservation
关键词 地毯厂生产废水 缺氧处理工艺 混凝沉淀处理工艺 production wastewater in carpet factory anoxic treatment process coagulation sedimentation treatment process
  • 相关文献

参考文献6

二级参考文献82

共引文献83

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部