摘要
以亚太森博如皋工厂工程为依托,对预应力混凝土管桩、劲性复合桩桩基方案技术与经济指标、施工可行性和质量可检性进行对比分析,并开展成桩工艺性试验。考虑施工工期、材料供应等因素,确定该工程采用劲性复合桩桩基方案。在劲性复合桩施工过程中,通过对水泥喷入量、水泥土搅拌均匀性、外桩与芯桩同心度偏差、垂直度偏差的关联施工参数进行有效管控,保证桩基施工质量。
On the basis of Aisa Symbol Rugao Factory Project,the technical and economic indicators,construction feasibility and quality checkability of prestressed concrete pipe pile and stiffened deep-cement-mixing pile were comparative analyzed,the pile-forming test was carried out.The final pile foundation scheme was determined after considering the construction period,material supply and other factors,which is the stiffened deep-cement-mixing pile.In the construction process,the quality of pile foundation engineering was ensured through implementing effective process management of the related four-indicator construction parameters,such as cement injection amount,soil-cement material stirring uniformity,concentricity deviation and verticality deviation of the soil-cementcolumn and pile core.
作者
马真祺
钱祖祥
张明坤
区钊文
黄俊
夏胞刚
MA Zhenqi;QIAN Zuxiang;ZHANG Mingkun;OU Zhaowen;HUANG Jun;XIA Baogang(Asia Symbol(Jiangsu)Pulp and Paper Co.,Ltd.,Nantong,Jiangsu 226537,China;Jiangsu Genuine-Strong Geotechnical Technology Co.,Ltd.,Nantong,Jiangsu 226019,China)
出处
《施工技术(中英文)》
CAS
2023年第9期73-77,共5页
Construction Technology
基金
江苏省产学研合作项目(BY2020176)。
关键词
劲性复合桩
管桩
成桩试验
水泥土
搅拌
同心度
垂直度
stiffened deep-cement-mixing piles
pipe piles
pile-forming tests
soil-cement material
stirring
concentricity
verticality