摘要
为满足离子膜一期扩能需求,通过对35kV离子高配系统组成情况进行分析,查找其存在的问题,针对问题进行技术攻关,实现了35kV离子高配及一期整流系统满足扩产的供电需求,提升系统的可靠性。
In order to meet the expansion demand of the first phase of the ion exchange membrane caustic soda plant,the composition of the 35 kv high-voltage distribution system was analyzed,the existing problems were identified,and technical research was carried out to address the problems.The 35 kV high-voltage distribution system and the first phase rectification system met the power supply demand for expansion,improving the reliability of the system.
作者
方宁
姜利平
丁卫星
FANG Ning;JIANG Li-ping;DING Wei-xing(Zhejiang Juhua Co.,Ltd.,Quzhou 324004,China)
出处
《中国氯碱》
CAS
2023年第6期1-5,共5页
China Chlor-Alkali
关键词
35kV离子高配
优化提升
综合改造
节能降耗
35 kV high-voltage distribution system
optimize and improve
comprehensive renovation
energy saving