深基坑工程地下水位突涨问题分析及处理 被引量:1

Analysis and Treatment of Sudden Rise of Groundwater Level in Deep Foundation Excavation Engineering
下载PDF
导出
摘要 长安九里768地块写字楼项目基坑设计深度为24.55m,根据前期地质勘察报告显示,地下水水位埋深在37.3~38.7m,因此基坑施工时未考虑降排水措施。在地下室施工阶段,永定河开始进行生态补水工作,受此影响,地块范围地下水水位大幅上涨,基坑内出现渗水,坑内积水深度最高达5.82m,极大影响基坑边坡安全,并且影响后续施工。针对该突发情况,采用围堰分仓排水的方式降低坑内积水水位,再通过浇筑水下混凝土对肥槽封底,排干积水后立即进行防水及肥槽回填施工,最大程度保证基坑安全性。 The design depth of the foundation excavation of the 768 block office building project in Jiuli,Chang’an is 2455m.According to the previous geological survey report,the groundwater level is buried at 373~387m,so the drainage measures were not considered during the foundation excavation construction.During the construction phase of the basement,Yongding River began to carry out ecological water replenishment.Affected by this,the groundwater level of the block area rose sharply,water seepage occurred in the foundation excavation,and the depth of water was up to 582m,which greatly affected the safety of the foundation excavation slope and the subsequent construction.In view of this sudden situation,separate cofferdam drainage is used to reduce the water level in the excavation,and then the bottom of the fertilizer tank is sealed by pouring underwater concrete.After draining the water,waterproof and fertilizer tank backfill construction are carried out immediately to ensure the safety of the foundation excavation to the maximum extent.
作者 柯江华 刘春青 王伟华 马建祥 贺娅梅 KE Jianghua;LIU Chunqing;WANG Weihua;MA Jianxiang;HE Yamei(The Fourth Branch of Zhongtian Construction Group Co.,Ltd.,Beijing 101113,China;Beijing Zhongtian North Construction Co.,Ltd.,Beijing 101113,China)
出处 《施工技术(中英文)》 CAS 2023年第11期77-81,共5页 Construction Technology
关键词 高层建筑 深基坑 沉降 围堰 渗水 处理 tall buildings deep foundation excavation settlement cofferdam water seepage treatment
  • 相关文献

参考文献6

二级参考文献48

共引文献50

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部