摘要
福溪水库为提升防洪能力,将原导流洞改建为泄放洞作为汛期预泄设施。主要介绍该水库泄放洞改造工程金属结构设备的总体布置和具体设计,并从设备布置、结构设计、启闭机选型等方面进行阐述,工程的金属结构在确保结构强度、刚度及稳定性的前提下均能符合现行规范要求。
In order to improve the flood control capacity of a reservoir,the original diversion tunnel was reconstructed into a discharge tunnel as a pre-discharge facility in flood season.This paper mainly introduces the general layout and specific design of the metal structure equipment in the discharge tunnel reconstruction project,and expounds the equipment layout,structural design,hoist selection and other aspects.The metal structure of the project can meet the requirements of the current code under the premise of ensuring the structural strength,stiffness and stability.
作者
何燕权
刘天祥
HE Yanquan;LIU Tianxiang(Jinhua Yongtai Hydropower Engineering Machinery Co.,Ltd.,Jinhua 321000,Zhejiang,China;Zhejiang Design Institute of Water Conservancy&Hydro-electric Power Co.,Ltd.,Hangzhou 310000,Zhejiang,China)
出处
《浙江水利科技》
2023年第4期85-88,共4页
Zhejiang Hydrotechnics
关键词
泄放洞
金属结构
工作闸门
事故检修闸门
设计
discharge tunnel
metal structure
service gate
emergency bulkhead gate
design