BIM技术在项目进度管理中的应用——以元阳高级中学为例

The Application of BIM Technology in Project Schedule Management——Taking Yuanyang Senior High School as an Example
下载PDF
导出
摘要 结合工程实例,利用BIM技术编制进度计划,采用BIM5D平台进行进度计划4D模拟及方案优化调整,进行实时跟踪,通过计划进度与实际进度对比分析,发现偏差后采取纠偏措施。结果表明基于BIM技术和5D平台,进度计划的编制及调整更加简单有效,进度模拟可以及时发现进度问题,缩短工期,降低成本,推动项目精细化管理。 In combination with engineering examples,the BIM technology is used to prepare the schedule plan,and the BIM5D platform is used to conduct the 4D simulation of the schedule plan and the optimization and adjustment of the plan,as well as real-time tracking.Through the comparison and analysis of the planned schedule and the actual schedule,the deviation is found and the corrective measures are taken.The results show that the preparation and adjustment of schedule plan based on BIM technology and 5D platform is more simple and effective,and schedule simulation can find schedule problems in time,shorten the construction period,reduce the cost,and promote the fine management of the project.
作者 容丽晖 RONG Li-hui(Dianchi College of Yunnan University,Kuning 650500,China)
出处 《工程建设与设计》 2023年第13期137-139,共3页 Construction & Design for Engineering
基金 2022年云南省教育厅科学研究基金项目(2022J1083)。
关键词 BIM技术 进度管理 4D模拟 BIMtechnology schedulemanagement 4D simulation
  • 相关文献

参考文献3

二级参考文献4

共引文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部