水利工程掘进机施工隧洞投资计算重难点 被引量:1

Key and Difficult Points in Investment Calculation of Tunnel Construction with Tunneling Machine in Water Conservancy Engineering
下载PDF
导出
摘要 以07版水利工程掘进机施工隧洞概算定额为分析基础,结合目前掘进机在水利工程中的实际应用情况及费用处理,研究使用定额合理分析掘进机施工隧洞工程投资的重难点:①单个项目中掘进机达不到寿命台时时,是否考虑重复利用;②购置成本如何处理。对此根据实际工程中相关费用的计算进行分析得出结论,并对现行定额修编提出相关建议。 Based on the analysis of 07 version of estimated quota for tunneling machine construction in water conservancy engineering,combined with the current practical application and cost management of tunneling machines,this paper studies the key and difficult points of using the quota to reasonably analyze the investment in tunneling machine construction.Firstly,when the service life of tunneling machine in a single project is not reached,should it be considered for reuse.Secondly,how to handle the acquisition cost.Based on the analysis of the calculation of relevant costs in actual engineering,conclusions have been drawn,and relevant suggestions have been put forward for the revision of current quota.
作者 杨林红 YANG Lin-hong(Yunnan Institute of Water&Hydropower Engineering Investigation,Design and Research,Kunming 650051,China)
出处 《云南水力发电》 2023年第7期296-299,共4页 Yunnan Water Power
关键词 水利工程 掘进机 设备购置费 隧洞开挖 water conservancy engineering tunneling machine equipment purchase cost tunnel excavation
  • 相关文献

参考文献3

二级参考文献15

共引文献56

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部