高温后套筒灌浆连接大变形反复拉压力学性能研究

STUDY ON MECHANICAL BEHAVIORS OF POST-FIRE GROUTED SLEEVE CONNECTIONS UNDER LARGE STRAIN OF CYCLIC LOADING
下载PDF
导出
摘要 套筒灌浆连接是预制混凝土结构当前钢筋连接的主要方式之一。基于套筒受力状态不明的问题,考虑高温作用的影响以及抗震需要,开展高温后(最高温度600℃)套筒灌浆连接试件的大变形反复拉压试验研究,探讨套筒应力分布与连接力学性能发展规律。当套筒灌浆料抗压强度为61.3 MPa时,试验结果表明:套筒环向处于弹性状态,但其中部的纵向将进入弹塑性受力状态;套筒灌浆连接试件失效模式由套筒外钢筋断裂转向钢筋与套筒灌浆料界面粘结滑移失效的关键温度为400℃;相对常温值,高温后试件的峰值载荷与峰值位移分别下降约为12%与17%。 Grouted sleeve connection is one of the main measures for steel rebar splicing of precast concrete structures at present.Aimed to figure out the stress state of sleeve,a post-fire grouted sleeve connection experiment with 12 specimens under large strain of cyclic loading was exerted to investigate the stress distribution development of sleeve and mechanical behaviors of the specimens by taking the elevated temperature and earthquake into account.There were lots of findings when the compressive strength of grout was 61.3 MPa as follows:the sleeve is in elastic state in the circumferential direction and elastic-plastic state in the longitudinal direction in the middle of the sleeve;the crucial temperature is 400℃ when the failure pattern of post-fire specimens changes from rebar fracture outside the sleeve to the bond slip failure between grout and steel rebar;compared to the values at ambient temperature,the peak load and peak displacement of the post-fire specimens decrease about 12% and 17% respectively.
作者 刘良林 LIU Lianglin(College of Building Engineering,Jinggangshan University,Ji’an 343009,Jiangxi,China)
出处 《力学与实践》 北大核心 2023年第3期535-543,共9页 Mechanics in Engineering
基金 江西省教育厅科技计划(GJJ201010) 吉安市科技支撑项目(吉市科计字2021[8]号工业5) 井冈山大学博士科研启动项目(JZB2208)资助。
关键词 套筒灌浆连接 高温作用 大变形反复拉压 失效模式 套筒应变 grouted sleeve connection elevated temperature large strain of cyclic loading failure pattern sleeve strain
  • 相关文献

参考文献6

二级参考文献34

  • 1肖建庄,刘良林,丁陶,张蕾.高温后套筒灌浆连接受力性能试验研究[J].建筑结构学报,2020,41(11):99-107. 被引量:11
  • 2余志武,王中强,史召锋.高温后新Ⅲ级钢筋力学性能的试验研究[J].建筑结构学报,2005,26(2):112-116. 被引量:44
  • 3陆洲导,朱伯龙.混凝土结构火灾后的检测方法研究[J].工业建筑,1995,25(12):37-41. 被引量:29
  • 4SUSANTHA K A S, HABIN G E, USAMI Tsutomu. Uniaxial stress-strain relationship of concrete confined by various shaped steel tubes[J]. Engineering Structures, 2000, 23 (21):1331-1347.
  • 5徐芝纶.弹性力学[M].北京:高等教育出版社,2006.
  • 6JGJl07--2010钢筋机械连接技术规程[S].北京:中国建筑工业出版社.2010.
  • 7LING J H, ABD RAHMAN A B, IBRAHIM I S, et al. Behaviour of grouted pipe splice under incremental tensile load[ J]. Construction and Building Materials, 2012, 33: 90-98.
  • 8MALVAR L J. Bond of reinforcement under controlled confinement[J]. ACI Materials Journal, 1992, 89(6) : 593-601.
  • 9MOOSAVI M, JAFARI A, KHOSRAVI A. Bond of cement grouted reinforcing bars under constant radial pressure [ J ]. Cement and Concrete Composites, 2005, 27( 1): 103-109.
  • 10郭正兴,郑永峰,刘家彬,等.一种钢筋浆锚对接连接的灌浆变形钢管套筒:ZL201320407071.4[P].2014-01-15.

共引文献144

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部