摘要
本文对江阴东国制钢CCL项目蓄热室氧化炉(RTO)设备安装工程的概况进行了叙述,首先分析设备安装工程的施工程序和施工方法,然后对电气安装的技术要求、仪器仪表安装的安装方案进行详细的研讨。
This article provides an overview of the installation engineering of the regenerative chamber oxidation furnace(RTO)equipment for the Jiangyin Dongguo Steel CCL project.Firstly,it analyzes the construction procedures and methods of the equipment installation engi⁃neering,and then conducts a detailed discussion on the technical requirements for electrical in⁃stallation and the installation plan for instrument and meter installation.
作者
王昊
Wang Hao(POSCO Construction(China)Co.,Ltd.,Shanghai 200122,CHN)
出处
《模具制造》
2023年第8期273-275,共3页
Die & Mould Manufacture
关键词
设备安装
机械安装
电气安装
仪表安装
equipment installation
mechanical installation
electrical installation
instrument installation