摘要
本文以重庆市新民水库为例,采用有限元法对水库主坝、副坝分别进行渗流计算。设定五种计算工况,经计算结果分析,大坝最大渗透比降为0.323,小于发生流土的允许比降;最大出逸比降为0.323,小于允许水力比降0.712。结合溢洪道、放水设施、反滤排水设施实地排查结果,工程渗流性态安全,评定新民水库大坝渗流安全等级为A级。
This paper takes Xinmin Reservoir in Chongqing City as an example and uses the finite element method to calculate the seepage of the main dam and auxiliary dam of the reservoir.Five calculation scenarios are set,and based on the computed results analysis,the maximum seepage coefficient of the dam is reduced to 0.323,which is lower than the allowable coefficient for soil erosion.The maximum outflow coefficient is 0.323,which is lower than the allowable hydraulic coefficient of 0.712.Combined with the on-site investigation results of spillways,discharge facilities,and anti-filtration drainage facilities,the seepage safety of the project is confirmed,and the seepage safety grade of Xinmin Reservoir dam is assessed as Class A.
作者
刘书军
LIU Shujun(Chongqing Vocational College of Transportation,Chongqing 402247,China)
出处
《水利建设与管理》
2023年第8期18-23,17,共7页
Water Conservancy Construction and Management
关键词
新民水库
渗流
安全评价
有限元法
Xinmin Reservoir
seepage
safety evaluation
finite element method