摘要 从发电机组直接冷却系统引海水设施的管材、施工方案两个方面,对海上及岸上引水方案进行综合比较,确定最经济合理的引水方案,为项目决策打下基础。从引水设施的管材、海上施工方案、岸上施工方案等角度进行分析对比,最终确定“岸上大开挖+支护、海上围堰+大开挖”为最优方案。 In this paper,from two aspects ofpipe material and construction scheme of diversion fcilitis of diret coling system of generator set.A comprehensive comparison is made between offshore and onshore diversion schemes to determine the most economical and reasonable diversion scheme,which lays a foundation for project decision-making.The paper analyzes and compares the pipe,offshore construction scheme and onshore construction scheme of water diversion fcities,and fnally delermines that"large excavation on shore+suppor,ofishore cofferdam+large excavation"is the optimal scheme.
作者 考传利 罗超 李娜 刘钢 赵米晗 张皓 KAO Chuan-li;LUO Chao;LI Na;LIU Gang;ZHAO Mi-han;ZHANG Hao(Anhui Conch Kawasaki Engineering Co.Ltd.,Wuhu 241000,China)
出处 《工程建设与设计》 2023年第11期223-225,共3页 Construction & Design for Engineering
关键词 发电机组 冷却系统 引海水方案 generating set,cooling system seawater water diversion project
  • 相关文献

参考文献2

二级参考文献6

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部