摘要 基于哈密一矿现有开采条件是否能满足双电厂用煤量的需求,分析了既有的轮斗挖掘机、破碎机核心采煤设备的生产能力,采场主干路咽喉区域道路通行能力,以及现有生产工艺开采条件下装车能力等影响因素。结果表明:在现有开采条件和开采工艺不变的情况下、核心采煤设备生产能力以及主干路咽喉区域通过能力可满足向双电厂供煤能力的要求。 Based on whether the existing mining conditions of Hami No.1 Mine can meet the demand of coal consumption of dual power plants,the article analyzes the production capacity of the existing wheel bucket excavator and crusher core mining equipment,road traffic capacity of the main road throat area of the stope,and the loading capacity under the existing production process mining conditions.The results show that the production capacity of core mining equipment and the passage capacity of the main road throat area can meet the requirement of coal supply capacity of dual power plants under the condition that the existing mining conditions and mining technology remain unchanged.
作者 宁大方 NING Dafang(China Coal Technology and Engineering Group Shenyang Design&Research Institute,Shenyang 110015,China)
出处 《露天采矿技术》 CAS 2023年第4期98-100,共3页 Opencast Mining Technology
关键词 轮斗挖掘机 破碎机 生产能力 通行能力 装车能力 wheel bucket excavator crusher production capacity traffic capacity loading capacity
  • 相关文献

参考文献5

二级参考文献8

共引文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部