期刊文献+

双优化目标下基于合同项目异质性的关键链项目群差别缓冲监控模型 被引量:1

Differential Buffer Monitoring Model of Key Chain Program Based on Contracted Project Heterogeneity in Double Optimization Objectives
下载PDF
导出
摘要 项目群是大型工程组织实施的基本形态。项目群涉及多个利益主体,合同项目延误会放大业主风险,为此,如何通过有效监控关键链项目群的缓冲、提升合同项目和项目群的按时完成率是降低业主风险的关键。首先,从业主需求偏好角度,将合同项目分为业主现值偏好型合同项目和工期偏好型合同项目;其次,根据综合效用,对关键链项目群缓冲进行分配,分别设置了两类合同项目的缓冲监控基准点;最后,研究并构建了业主不同需求偏好下基于合同项目异质性的关键链项目群缓冲监控方法,同时,提出了缓冲监控基准点的纠偏措施。仿真结果表明,与传统的静态统一缓冲监控方法相比,差别监控方法能够实现项目群业主现值和工期的双优化,并提高了合同项目和项目群的按时完成率。 Program is the basic form of large-scale project organization and implementation.Since the program involves multiple stakeholders,the construction delay of the contracted project will amplify the risk of the employer.Therefore,how to improve the on-time completion probability of the contracted project,milestone contracted project and program through the effective monitoring of the buffer of the key chain program is the key to reducing the risk of the employer.First,from the perspective of the employer’s demand preference,the contracted project is divided into the employer’s present value preference contracted project and duration preference contracted project.Then,by analyzing the characteristics of milestone contracted projects,this paper studies and constructs the buffer monitoring model of key chain program based on the heterogeneity of contracted projects under different employer’s demand preferences.Finally,the buffer of key chain program is allocated according to the comprehensive utility,and different buffer monitoring benchmarks are set for the two types of contracted projects.At the same time,in combination with the milestone contracted project,the deviation correction measures of buffer monitoring benchmark are proposed.The simulation results show that compared with the traditional static unified buffer monitoring method,the differential monitoring method can realize the double optimization of the employer’s present value and construction period of the projected group at the same time,and improve the on-time completion probability of contracted projects,milestone contracted projects,and programs.
作者 丰景春 聂蕊琪 张可 FENG Jingchun;NIE Ruiqi;ZHANG Ke(Business School,Hohai University,Nanjing 211100,China;Institute of Project Management,Hohai University,Nanjing 211100,China;Jiangsu Provincial Collaborative Innovation Center of World Water Valley and Water Ecological Civilization,Nanjing 211100,China)
出处 《系统管理学报》 CSCD 北大核心 2023年第5期901-915,共15页 Journal of Systems & Management
基金 国家社会科学基金资助项目(17BGL156) 河海大学中央高校基本科研业务费项目(B220207039) 住房和城乡建设部2018年科学技术项目(2018-K8-23) 南京市建委科技项目计划(Ks2114)。
关键词 关键链项目群管理 合同项目异质性 业主现值-工期优化 key chain program management heterogeneity of contracted projects employer’s present value-duration optimization
  • 相关文献

参考文献19

二级参考文献148

共引文献126

同被引文献10

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部