摘要
文章介绍了西淝河北站深大基坑施工降排水方法比选及降排水方案设计,通过抽水试验验证了方案的可行性、有效性。
Through comparison,this paper discusses the drainage methods of the large-scale deep foun-dation pit of the Xifeihe River North Station Project,briefly describes the design of the foundation pit dewatering scheme,and verifies the feasibility and effectiveness of the scheme through the pumping test.
作者
刘承训
姚军平
LIU Chengxun;YAO Junping(Anhui Technical College of Water Resources and Hydroelectric Power,Hefei 231603,China;Anhui Yuyao Engineering Construction Co.,Ltd,Hefei 230000,China)
出处
《安徽水利水电职业技术学院学报》
2023年第3期1-4,共4页
Journal of Anhui Technical College of Water Resources and Hydroelectric Power
关键词
深大基坑
管井降水
抽水试验
large-scale deep foundation pit
tube dewatering
pumping test