摘要
中牟大工是清廷举全国之力堵口的大型工程,是黄河治理史上的重要大事。从道光二十三年(1843年)六月黄河发生漫水至道光二十四年初合龙失利,中牟大工首次合龙过程历经五个阶段。首先在漫口之南准备修筑遥堤,次之转向裹头盘筑、工程估算、合龙备战,继之善后估算。与此相应,所绘21幅黄河古地图,再现了此次中牟大工首次合龙的具体过程,构成了一幅幅连续、动态的历史画像,为研究清代中央与地方互动提供了图像证据。这种事件史视域下的古地图研究方法,为其他主体地图研究提供了借鉴。
The Zhongmu Closure Project was a monumental endeavour undertaken by the Qing government and a significant event in the history of regulating the Yellow River.From the breaching of the dykes in the six month of the twenty-third year in the Daoguang period(1843)to the failure of the first closure in the next year(1844),the project's first river closure was carried out in five stages.In the beginning,efforts were taken to construct a distant embankment south of the crevasse.Subsequently,attention was shifted to reinforcing the dykes at the crevasse,making evaluation and budget,preparing for the closure,and giving an assessment of the aftermath.In a continuous and dynamic way,twenty-one maps record the historical process of this river closure,providing pictorial evidence for studying the interactions between the central and local governments during the Qing dynasty.Research on ancient maps from the perspective of event history will shed light on other cartographic studies.
出处
《中国国家博物馆馆刊》
北大核心
2023年第9期92-108,共17页
Journal of National Museum of China
基金
国家社会科学基金重点项目“中国藏珍稀黄河古地图整理与研究”(项目批准号:21AZD128)
国家新闻出版署“十四五”重点图书出版项目“海内外珍稀黄河古地图整理与黄河治理保护研究”“宁夏哲学社会科学领军人才工程”阶段性成果。
关键词
中牟大工
地图绘制过程
事件史
道光二十三年
Zhongmu Closure Project
mapping
event history
twenty-third year of Daoguang period(1843)