期刊文献+

两台阶法在倒虹吸基坑开挖施工中的应用

Application of Two Step Method in Excavation Construction of Inverted Siphon Foundation Pit
下载PDF
导出
摘要 通过对往期工程案例的分析,在深基坑明挖施工过程中,开挖方法的选择和运输便道的规划布置直接影响基坑开挖的施工效率、施工成本等。基于设计图纸及现场实际情况,针对珠三角水资源配置工程大岭山倒虹吸开挖施工,研究使用两台阶法进行开挖施工的步骤和相关措施。同时,对开挖过程中可能出现的问题以及解决的措施进行了细致的讨论。 Through the analysis of previous engineering cases,the selection of excavation methods and the planning and layout of transportation roads directly affect the construction efficiency and cost of deep foundation pit excavation during the open excavation construction process.Based on the design drawings and actual onsite conditions,this article studies the steps and related measures of using the two-step method for excavation construction of the Dalingshan inverted siphon in the Pearl River Delta water resource allocation project.At the same time,it has conducted a detailed discussion on the possible problems that may arise during the excavation process and the measures to be taken to solve them.
作者 曹达政 吴健林 马云川 CAO Da-zheng;WU Jian-lin;MA Yun-chuan(POWERCHINA SINOHYDRO ENGINEERING BUREAU 14 CO.,LTD.,Kunming 650041,China)
出处 《云南水力发电》 2023年第10期93-97,共5页 Yunnan Water Power
关键词 深基坑 运输便道 倒虹吸 两台阶法 deep foundation pit transportation access road inverted siphon two step method
  • 相关文献

参考文献7

二级参考文献9

共引文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部