基于遗传算法的工程进度款支付策略比选

Comparison and Selection of Project Progress Payment Strategy Based on Genetic Algorithm
下载PDF
导出
摘要 针对建筑工程工期-成本优化问题,考虑资金时间价值,结合施工费用与进度款的支付时间,以财务净现值作为最终评价指标,建立基于遗传算法的计算模型并开发相应程序。算例表明,在考虑与不考虑资金时间价值的不同情况下,得到的最优方案不一定一致,而在考虑资金时间价值的情况下采取的最优方案其财务净现值更大,可在实际工程中推广运用。 In view of the optimization of construction period cost,considering the time value of capital,combining the payment time of construction cost and progress payment,and taking the financial net present value as the final evaluation index,the study establishes a calculation model based on genetic algorithm,and develops the corresponding program.In order to verify its rationality,it is compared by an example,which shows that the optimal scheme is not necessarily the same when considering and not considering the value of time.Because the model considers the time value of capital,the conclusion is more reasonable,and it can be promoted in practical projects.
作者 华中驰 Hua Zhongchi(Lishui Vocational and Technical College,Lishui 323000,China)
出处 《黑龙江科学》 2023年第20期84-87,共4页 Heilongjiang Science
关键词 工期-成本优化 遗传算法 财务净现值 资金时间价值 MATLAB用户界面 Duration-cost optimization Genetic algorithm Financial net present value Time value of capital MATLAB user interface
  • 相关文献

参考文献3

二级参考文献20

  • 1Kamara J M,Anumba C J,Evbuomwan N F O.Assessing the suitability of current briefing practices in construction with a concurrent engineering framework[J].International Journal of Project Management,2001,19(6):337-351.
  • 2Maheswari J U,Varghese K,Sridharan T.Application of dependency structure matrix for activity sequencing in concurrent engineering projects[J].Journal of Construction Engineering and Management,2006,132(5):482-490.
  • 3Winner R I,Pennell J P,Bertrand H E,et al.The role of concurrent engineering in weapons system acquisition[R].Virginia:Institute for Defense Analyses,1988.
  • 4Altus S S,Kroo I M,Gage P J.A genetic algorithm for scheduling and decomposition of muhidisciplinary design problems[J].Journal of Mechanical Design,1996,118 (4):486--489.
  • 5Austin S,Baldwin A,Li B,et aL Analytical design planning technique (ADEPT):a dependency structure matrix tool to schedule the building design process[J].Construction Management and Economics,2000,18 (2):173-182.
  • 6Steward D V.System analysis and management:Structure,strategy and design[M].New York:Petrocelli Books,1981.
  • 7Browning T R,Eppinger'S D.Modeling impacts of process architecture on cost and schedule risk in product development[J].IEEE Transactions on Engineering Management,2002,49(4):428-442.
  • 8Meier C,Yassine A A,Browning T R.Design process sequencing with competent genetic algorithms[J].Journal of Mechanical Design,2007,129(6):566-585.
  • 9Butcher WS. Dynamic programming for project cost-time curve.Journal of Construction Division, ASCE 1967, 93 (C01): 59~ 73
  • 10Panagiotakopoulos D. Cost-time model for large CPM project networks. Journal of Construction Engineering and Management, ASCE 1977; 103 (C02): 201~11