摘要
寻乌县太湖水库是一座中型水利枢纽工程,坝型为混凝土面板堆石坝。坝体堆石料场规划的合理性直接决定大坝填筑能否按期顺利完工。对堆石料场开采规划方法作了详细的说明,并由此得出堆石坝石料场施工前期地质复查、料场开采分层分块及底高程确定对堆石坝施工工期和经济效益具有十分重要的作用。
The Taihu Lake Reservoir in Xunwu County is a medium-sized water control project.The dam type is concrete face rockfill dam.The rationality of the planning of the dam rockfill yard directly determines whether the dam filling can be completed smoothly on schedule.A detailed explanation of the mining planning method for the rockfill dam quarry was provided,and it was concluded that the geological review in the early stage of the construction of the rockfill dam quarry,the layering and blocking of the quarry mining,and the determination of the bottom elevation play a very important role in the construction period and economic benefits of the rockfill dam.
出处
《山西水利科技》
2023年第3期1-4,7,共5页
Shanxi Hydrotechnics
关键词
料场复查
储量分析
开采范围规划
分层分块规划
quarry review
reserve analysis
mining range planning
stratification and partitioning planning