摘要 52305综采工作面为右工作面,工作面长度为322.15 m,推进长度2076.67 m,设计采高3.1 m,煤层厚度2.5~3.5 m。52305工作面地表为黄土沟壑区,地表标高1216~1334 m,最大高差118 m;回采面上部有43煤层的43204综采采空区、43205综采采空区,层间距58~63m;对工作面初次来压及周期来压,特殊地质条件下来压情况进行了详细介绍,对类似综采工作面的回采具有指导意义。 The 52305 fully mechanized mining face is a right working face with a length of 322.15 m,a advancing length of 2076.67 m,a design mining height of 3.1 m,and a coal seam thickness of 2.5-3.5 m.The surface of 52305 working face is in a loess gully area,with a surface elevation of 1216-1334 m and a maximum elevation difference of 118 m.There are 43204 and 43205 fully mechanized goafs of 43 coal seam in the upper part of the mining face,with a layer spacing of 58-63 m.A detailed introduction is given to the initial pressure and periodic pressure of the working face,as well as the pressure situation under special geological conditions,which has guiding significance for the future recovery of similar fully mechanized working faces.
作者 刘兆祥 李瑞楼 卞涛 LIU Zhaoxiang;LI Ruilou;BIAN Tao(Bulianta Coal Mine,CHN Energy Shendong Coal Group Co.,Ltd.,Erdos 017209,China)
出处 《中国矿业》 2023年第S02期163-167,共5页 China Mining Magazine
关键词 综采工作面 矿压规律 初次来压 周期来压 回采 fully mechanized mining face mine pressure pattern initial pressure periodic pressure recovery
  • 相关文献

参考文献6

二级参考文献75

共引文献110

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部