摘要
以重庆某超高层项目为例对其冷热源系统方案的选择过程进行论述,并从各备选冷热源方案自身的技术特点、能效性、初投资、运行成本、后期维护等方面进行比较,经分析得出水冷电制冷冷水机组加锅炉的冷热源形式为本项目最优解。
This paper takes a super high building in Chongqing as an example,introduces the selection process of cold and heat source system scheme,and compares the alternative cold and heat source schemes from own technical characteristics,energy efficiency,initial investment,operation cost,maintenance,etc.The water-cooled electric cooling chiller plus boiler with cold and heat source form is proved to be the optimal solution of this project.
作者
周梦琦
Zhou Mengqi(China Architectural Design and Research Institute Co.,Ltd.,Beijing,100044)
出处
《建设科技》
2023年第18期62-64,共3页
Construction Science and Technology
关键词
冷热源
水冷电制冷冷水机组
锅炉
风冷热泵
初投资及运行费用
cold and heat source
water-cooled electric cooling chiller
boiler
air-cooled heat pump
initial investment and operation costs