摘要
针对九日山危岩体存在崩塌、滑移、倾倒的问题,论文以九日山危岩体为例,叙述了常见的加固措施,分析了危岩体机理现状,同时针对其成因进行了探究,采用微型锚杆结合裂隙灌浆和砌筑的方法解决了石刻周边危岩体存在的安全隐患,对石刻本体的保护起到了极其重要的作用。结果表明:以锚杆为主的加固以及以砌筑为主的加固方法的运用,均有利于提高危岩的稳定性。
Aiming at the problems of collapse,slip and toppling of the dangerous rock mass in Jiuri Mountain,taking Jiuri Mountain dangerous rock mass as an example,this paper describes the common reinforcement measures,analyzes the mechanism of dangerous rock mass,and explores its causes.Micro-anchor combined with crack grouting and masonry are adopted to solve the safety risks of dangerous rock mass around the stone carvings,which plays an extremely important role in protecting the stone carvings.The results show that the use of bolting as the main reinforcement method and masonry as the main reinforcement method is conducive to improving the stability of dangerous rock.
作者
何春燕
HE Chun-yan(Nan’an Jiuri Mountain Cultural Protection and Management Center,Nan’an 362300,China)
出处
《工程建设与设计》
2023年第18期181-183,共3页
Construction & Design for Engineering
关键词
九日山
摩崖石刻
危岩体
成因分析
加固方法
Jiuri Mountain
inscriptions on precipices
dangerous rock mass
cause analysis
reinforcement method