地铁车站施工部署优化设计

Optimization design of subway station construction deployment
下载PDF
导出
摘要 在地铁车站的施工过程中,常发生施工顺序及进度的变更,必须通过优化结构设计或者调整施工部署解决上述冲突。文章以某地铁车站建设项目为案例,采用理正单元计算,与Midas整体计算对比了提前插入主体结构施工对基坑的安全性的影响,并针对所采用的盖挖逆作法进行调整,对其安全施工提出了建议。 In the process of subway station construction,the construction sequence and schedule are often changed,and the above conflicts must be solved by optimizing the structural design or adjusting the construction deployment.This paper presents a case study of a subway station construction project,comparing the impact of early insertion of main structural construction on the safety of excavation using Lizheng unit calculations and Midas comprehensive calculations.Adjustments are proposed for the adopted top-down excavation method to ensure safe construction.
作者 陈强 CHEN Qiang(China Railway 11th Bureau Group Third Engineering Co.,Ltd.,Shiyan 442012,China)
出处 《中国高新科技》 2023年第15期67-69,共3页
关键词 基坑 支护 MIDAS 理正计算 excavation support Midas Lizheng calculations
  • 相关文献

参考文献3

二级参考文献12

共引文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部