摘要
吊杆张拉是系杆拱桥施工中的重要环节,吊杆的张拉顺序不同会对结构内力分布及变形产生不同的影响。为了研究吊杆张拉顺序对钢箱系杆拱桥结构受力的影响,以新建湄池大桥主桥为工程背景,借助有限元软件midas Civil 2020建立桥梁三维仿真模型,对比分析了三种吊杆张拉顺序下的结构预拱度和内力变化规律。计算结果表明,从跨中对称向两端张拉是吊杆张拉施工的最优方案。
The tension of suspender cable is an important link in the construction of tied arch bridge.The internal force distribution and deformation of the structure will be affected by the different tension order of boom cable.In order to study the influence of the tension sequence of boom cable on the structural stress of steel box tied arch bridge,a 3D simulation model of the new built Meichi Bridge is built by the finite element software midas Civil 2020,analyzed the law of change of precamber and internal force of the structure under three kinds of boom cable tension sequence.The results show that stretch symmetrically from the middle of the span to the both ends is the best scheme for the construction of the suspender cable.
作者
宗纪兵
王云
ZONG Ji-bing;WANG Yun(CCEED Investment and Development Company,Ningbo,Zhejiang 315400,China;Shandong Luzheng Engineering Project Management Consulting Co.,Ltd.,Jinan,Shandong 261000,China)
出处
《黑龙江交通科技》
2023年第11期98-100,104,共4页
Communications Science and Technology Heilongjiang
关键词
钢箱系杆拱桥
吊杆张拉顺序
预拱度
成桥索力
steel box tied arch bridge
suspender tension sequence
precamber
completed cable force