深圳固戍水质净化厂二期工程EPC项目BIM技术应用 被引量:2

Application of BIM Technology in Gushu Water Purification Plant PhaseⅡEPC Project in Shenzhen
原文传递
导出
摘要 深圳固戍水质净化厂二期工程设计规模32×10^(4)m^(3)/d,占地面积15.14 hm^(2),具有工程体量大、单体多、构造复杂等特点。项目设计中采用精细化的BIM设计和定量化的仿真分析,力求提升项目设计品质,减少后期变更。同时定制一套基于BIM的工程协同管理平台,对施工过程中的图纸、模型、投资、质量、进度、安全、设备等进行集中管理。通过阐述项目设计、施工中的重点BIM应用,总结了BIM应用过程和方法,以期为水质净化厂BIM设计、EPC管理提供经验。 The design scale of Gushu water purification plant phaseⅡproject in Shenzhen is 32×10^(4)m^(3)/d.The project covers a footprint area of 15.14 hm2,and has the characteristics such as large quantities,many single treatment units and complex structure.In the design of the project,refined BIM design and quantitative simulation analysis were adopted to improve the design quality of the project and reduce late changes.In addition,a set of BIM‑based project collaborative management platform was customized to centrally manage drawings,models,investment,quality,schedule,safety and equipment in the construction process.By elaborating on the key application of BIM in project design and construction,this paper summarized the BIM application process and methods,so as to provide experience for BIM design and EPC management of water purification plants.
作者 吴迪 王宇婷 WU Di;WANG Yu‑ting(Central&Southern China Municipal Engineering Design&Research Institute Co.Ltd.,Wuhan 430010,China)
出处 《中国给水排水》 CAS CSCD 北大核心 2023年第22期66-72,共7页 China Water & Wastewater
关键词 水质净化厂 EPC管理 BIM应用 仿真分析 water purification plant EPC management BIM application simulation analysis
  • 相关文献

参考文献4

二级参考文献38

  • 1邓雪原.CAD、BIM与协同研究[J].土木建筑工程信息技术,2013,5(5):20-25. 被引量:60
  • 2H Edward Goldberg. AEC From the Ground Up:The Building Information Model[J].CADalyst Eugene,2004.56-58.
  • 3Faraj I,Alshawi M,Aouad G,Child T,Underwood J. Industry foundation classes Web-based collaborative construction computer environment:WISPER[J].Automation in Construction,2000.79-99.
  • 4Halfawy,Mahmoud M.R,Froese,Thomas M. Component-based framework for implementing integrated architectural/engineeringc/construction project systems[J].Journal of Computing in Civil Engineering ASCE,2007.441-452.
  • 5张建平;张洋;张新.基于IFC的BIM及其数据集成平台研究[A]浙江杭州,2008227-232.
  • 6Kam,Calvin,Fischer,Martin,Hanninen,Reijo,Lehto,Seppo,Laitinen,Jarmo. Implementation challenges and research needs of the IFC interoperability standard:Experiences from HUT-600 construction pilot[R].American Society of Civil Engineers.Washington,DC,United states,2002.
  • 7Pazlar,Tomaz,Turk,Ziga. Interoperability in practice:Geometric data exchange using the IFC standard[J].Electronic Journal of Information Technology in Construction,2008.362-380.
  • 8曹政国,吴刘忠球,李致,邵国霞.BIM在铁路施工组织设计中的应用探讨[J].铁道工程学报,2018,35(12):99-103. 被引量:27
  • 9胡振中,彭阳,田佩龙.基于BIM的运维管理研究与应用综述[J].图学学报,2015,36(5):802-810. 被引量:171
  • 10杨小琴.铁路项目建设中工程物资管理的相关问题探讨[J].中小企业管理与科技,2016(1):51-51. 被引量:5

共引文献100

同被引文献18

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部