摘要
地下厂房及平硐的安全开挖和高效施工,是抽水蓄能电站工程可研阶段的重要工程阶段。本文结合某抽水蓄能电站地下硐室开展的放射性元素及有害气体测试,详细说明各种工程阶段中常见的有害气体和放射性元素的检测、标准及评价,为该工程的顺利开展发挥了至关重要作用。
Safe excavaton and fficient contruction of underground powerhouse and adit is an important engineering stage in the feasibility stage of pumped storage power station project.Based on the test of radioactive elements and harmful gases caried out in the underground chamber of a pumped storage power station,this paper describes in detail the detection,standards and evaluation of common harmful gases and radioactive elements in various engineering stages,which plays a vital role in the smooth development of the project.
作者
宋伟健
陈鑫
刘金锋
SONG Wei-jian;CHEN Xin;LIU Jin-feng
出处
《东北水利水电》
2023年第12期40-41,68,72,共4页
Water Resources & Hydropower of Northeast China
关键词
抽水蓄能电站
平硐
放射性元素
有害气体
pumped storage power station
adit
radioactive elements
harmful gases