摘要
文中以萨摩亚法莱奥诺国际机场升级改造项目为研究背景,分析了不停航条件下机场升级改造中分阶段施工的方案,研究如何在项目管理中合理安排不停航施工。以优化项目进度和资源利用为目的,结合PERT/CPM模型与项目管理方法,针对不停航施工的项目中各项控制要素进行优化管理,并在萨摩亚法莱奥诺国际机场升级改造项目中验证其有效性。
Based on the research background of the renovation project of Faleono International Airport in Samoa,this paper studies how to rationally arrange non-stop construction in project management through the selection of the phased construction scheme in the airport upgrade and renovation under non-stop traffic conditions.In order to optimize the project schedule and resource utilization,by combining PERT/CPM model and project management method,the control elements of non-stop construction projects were optimized and managed,and the effectiveness was verified in the upgrade and renovation project of Faleono International Airport in Samoa.
作者
徐志伟
Xu Zhiwei(Shanghai Construction Group Co.Ltd.,Shanghai 200032)
出处
《江西建材》
2023年第9期350-353,共4页
Jiangxi Building Materials