期刊文献+

一起220kV主变乙炔严重超标事件原因分析与处理

Cause Analysis and Treatment of Serious Exceeding of Acetylene in 220kV Main Transformer
下载PDF
导出
摘要 通过一起220kV主变压器乙炔严重超标事件的分析与处理,指出造成本次事故的根本原因在于拉杆安装时不满足厂家装配要求,详细说明了GOE拉杆式套管的结构与原理,提出了对于同类型设备的排查思路和事故预防措施。 Through the analysis and treatment of a 220kV main transformer acetylene seriously exceeding the standard,it is pointed out that the root cause of the accident is that the tie rod installation does not meet the manufacturer's assembly requirements,the structure and principle of GOE pull rod type bushings are explained in detail,and the investigation ideas and accident prevention measures for the same type of equipment are put forward.
作者 何天磊 胡磊 王晓剑 梁辰 徐俊元 陈聪 HE Tian-lei;HU Lei;WANG Xiao-jian;LIANG Chen;XU Jun-yuan;CHEN Cong(China Power Hua Chuang Electricity Technology Research Co.,Ltd.,Shanghai 200086,China;China Power Hua Chuang(Suzhou)Electricity Technology Research Co.,Ltd.,Suzhou 215123,China)
出处 《变压器》 2023年第11期68-71,共4页 Transformer
关键词 主变 乙炔 套管 预防措施 Main transformer Acetylene Bushing Preventive measure
  • 相关文献

参考文献21

二级参考文献316

共引文献101

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部