摘要
研究了建筑工程建设中通风与空调系统的调试过程,分析了通风与空调系统调试对于提供舒适的室内环境、保障人员健康和安全,以及提高能源利用效率的重要意义,指出了在调试前的准备工作中,需要进行机电调试策划、调试人员和仪器的组织,以及完成调试方案和图纸的编制,并对调试过程中涉及水系统、防排烟系统和空调风系统的测试和调整提出了相应的解决办法。
This paper studies the debugging process of ventilation and air conditioning system in building engineering construction.We realize that the debugging of ventilation and air conditioning system is of great significance for providing a comfortable indoor environment,ensuring the health and safety of personnel and improving the efficiency of energy utilization.In the preparation before debugging,it is necessary to plan the electromechanical debugging,organize the debugging personnel and instruments,and complete the compilation of debugging scheme and drawings.During the debugging process,it involves the testing and adjustment of water system,smoke control system and air conditioning system.In view of the common problems,the corresponding solutions are put forward.
作者
吴海
WU Hai(China Construction Second Bureau Installation Engineering Co.Ltd.,Beijing 100000,China)
出处
《工程建设与设计》
2023年第23期55-57,共3页
Construction & Design for Engineering
关键词
建筑工程
通风与空调系统
调试
construction engineering
ventilation and air conditioning system debug