某工程根据具体施工条件,经研究采用分期导流,一期围右岸,二期围左岸的导流设计方案,既能满足工程施工现场导截流和安全度汛的需求,又可以使水库大坝连续快速施工,为安全、可靠、节能、经济且高效的施工奠定基础,使得工程后续阶段的工作顺利开展。
Based on specific construction conditions,the project adopts a phased diversion design scheme,with the first phase enclosing the right bank and the second phase enclosing the left bank.It can not only meet the needs of river diversion and safe flood control at the construction site,but also enable the continuous and rapid construction of the reservoir dam,laying the foundation for safe,reliable,energy-saving,economical and efficient construction,and ensuring the smooth progress of the subsequent stages of the project.
作者
罗明华
LUO Minghua(Power China Gansu Energy Investment Co.,LTD.,Lanzhou 730000,China)
出处
《云南水力发电》
2023年第12期344-348,共5页
Yunnan Water Power
关键词
中型水库
工程地质
导流方式比选
导流建筑物设计
导流施工
medium reservoir
engineering geology
comparison and selection of diversion methods
design of diversion structure
diversion construction