摘要
顶管工程埋深是决定工程安全的关键因素,在满足规范要求的基础上,需经过土层及挖掘面的稳定性计算、地面荷载的影响分析后,结合工程经验综合确定。
The burial depth of the pipe jacking project is a key factor for project safety.On the basis of meeting the requirements of the specifications,it is necessary to comprehensively determine the burial depth after stability calculations on the soil layer and excavation surface,and impact analysis of ground loads,combined with engineering experience.
出处
《山西水利科技》
2023年第4期4-6,共3页
Shanxi Hydrotechnics
关键词
顶管
埋深
稳定
pipe jacking
burial depth
stability