EBIS工艺在全地下污水处理厂改造中的应用

Application of EBIS Process in Reconstruction of Underground Sewage Treatment Plant
原文传递
导出
摘要 大连市某全地下污水处理厂处理规模为8000 m^(3)/d,原采用BF-A/O摇动床处理工艺,出水水质执行《城镇污水处理厂污染物排放标准》(GB 18918—2002)一级A标准。原BF-A/O工艺缺少厌氧段,无化学除磷措施,缺氧及好氧停留时间远小于设计停留时间,导致总磷及总氮超标,而现状全地下污水厂改造空间局促、改造周期较短且系统不能停车。本次选择的高效一体化生物处理系统(EBIS)工艺在原调节池、BF-A/O摇动床及消毒池体中进行改造,将原清水池改造为磁混凝系统,强化化学除磷,分组分期进行改造,对原土建池体充分利用,极大缩短了改造周期,同时保证系统不停车。试运行结果表明,经过EBIS-磁混凝系统处理后,出水水质稳定达到一级A标准。项目实际总投资为3803.90万元,新增直接运行成本为0.40元/m^(3)。 The treatment scale of an underground sewage treatment plant in Dalian is 8 000 m^(3)/d.The original key process is BF-A/O shaking bed,and the effluent quality is required to meet the first level A limit specified in the Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant(GB 18918-2002).The original BF-A/O process lacks anaerobic section and chemical phosphorus removal measures,and the residence times of anoxic and aerobic tanks are far less than the designed values,resulting in the total phosphorus and total nitrogen exceeding the discharge standard.The space of the reconstruction project is limited,and the construction needs to be completed in a short period without suspending production.The original regulating tank,BF-A/O shaking bed and disinfection tank were transformed into the energy biochemical intelligent control system(EBIS) process,and the original clear water reservoir was transformed into a magnetic coagulation system to improve the chemical phosphorus removal.The project was carried out in different groups and stages,and the original civil structures were highly utilized,which greatly shortened the transformation period without suspending production.The trial operational results showed that the effluent quality met the first level A limit after being treated by the EBIS-magnetic coagulation system.The actual total investment of the project is 38.039 million yuan,and the direct operating cost is increased by 0.40 yuan/m^(3).
作者 曹猛 陈海 CAO Meng;CHEN Hai(Dalian Municipal Design&Research Institute Co.Ltd.,Dalian 116011,China)
出处 《中国给水排水》 CSCD 北大核心 2023年第24期82-86,共5页 China Water & Wastewater
关键词 一体化生物处理系统(EBIS) 全地下污水处理厂 磁混凝 BF-A/O摇动床 energy biochemical intelligent control system(EBIS) underground sewage treatment plant magnetic coagulation BF-A/O shaking bed
  • 相关文献

参考文献4

二级参考文献25

  • 1樊芸,杨凤林,张兴文,石利军,谷川宪治.摇动床生物膜反应器处理生活污水[J].环境污染与防治,2005,27(9):683-685. 被引量:6
  • 2石利军,荀钰娴,杨凤林,张兴文,王旭江,古川宪治.A/O摇动床石化废水生物脱氮[J].化工学报,2006,57(1):104-108. 被引量:7
  • 3殷永泉,邓兴彦,刘瑞辉,张凯,崔兆杰.石油化工废水处理技术研究进展[J].环境污染与防治,2006,28(5):356-360. 被引量:65
  • 4Rouse,J.D.,Yazaki,D.,Cheng,Y.,et al.Swim-bed technology as an innovative attached-growth process for high-rate wastewater treatment.Japanese Journal of Water Treatment Biology,2004,40 (3):115 - 124.
  • 5Ha D.T.,Kutsumoto R.,Koyama T.,et al.Nitrification of ammonium-contaminated hanoi groundwater using swim-bed technology.Japanese Journal of Water Treatment Biology,2005,41 (3):141 -152.
  • 6Yamamoto T.,Takak i K.,Koyama T.,et al.Novel partial nitritation treatment for anaerobic digestion liquor of swine wastewater using swim-bed technology.Journal of Bi-oscience and Bioengineering,2006,102 (6):497 -503.
  • 7Ha D.T.,Kutsumoto R.,Koyama T.,et al.Evaluation of the swim-bed attached-growth process for nitrification of hanoi groundwater containing high levels of iron.Japanese Journal of Water Treatment Biology,2005,41 (4):.181 -192.
  • 8Partial nitritation of raw anaerobic sludge digester liquor by swim-bed and swim-bed activated sludge processes and comparison of their sludge characteristics.Journal of Biosci-ence and Bioengineering,2008,106(5):433-441.
  • 9GB/T5750.4-2006,生活饮用水标准检验方法感官性状和物理指标.
  • 10国家环保总局《水和废水监测分析方法》编委会.水和废水监测分析方法(第3版)[M].北京:中国环境科学出版社,1989.189.

共引文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部