带压开采工作面导水陷落柱综合勘察治理技术

Comprehensive Investigation and Treatment Technology of Water Conductivity Collapse Column in Pressure Mining Face
下载PDF
导出
摘要 为避免矿井在回采过程中遇陷落柱突水而导致的安全事故,保证工作面安全回采,在马道头煤业8106回采工作面通过陷落柱前进行勘察治理。根据物探结果,在5106顺槽切眼前方1 080~1 140 m范围内存在富水异常区;根据物探及钻探结果,施工加固治理钻孔37个,水泥注浆量63.84 t。治理后物探结果与治理前区域进行对比,未发现明显异常区。 In order to avoid safety accidents caused by water inrush from collapsed pillars during the mining process of the mine and ensure safe mining of the working face,investigation and treatment have been carried out before the 8106 mining face passes through the collapsed pillars.The geophysical exploration results indicate that there is a water rich anomaly area within the range of 1080-1140 m in front of the 5106 entry cut.37 boreholes have been drilled for construction reinforcement and treatment,with a cement grouting volume of 63.84 tons,which proves that there are no obvious abnormal areas.
作者 李鹏举 Li Pengju(Madaotou Coal Industry Co.,Ltd.,Jinneng Holding Coal Industry Group,Datong,Shanxi 037000)
出处 《江西煤炭科技》 2024年第1期118-120,124,共4页 Jiangxi Coal Science & Technology
关键词 回采工作面 带压开采 陷落柱 注浆加固 物探和钻探 working face mining with water pressure collapse column grouting reinforcement geophysical exploration and drilling
  • 相关文献

二级参考文献39

共引文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部