摘要
简单介绍了煤层气的开发现状,针对煤层气项目在建设过程中存在的周期较长的问题,可通过在设计环节对井场、集气站进行标准化设计来优化。并对目前比较常规的几种项目规模,给出了相应的建议设备布置,以期能够缩短项目周期。
This paper briefly introduces the development status of coalbed methane.Aiming at the problem that the coalbed methane project has a long period in the construction process,it can be optimized by standardizing the design of well sites and gas gathering stations in the design process.And for several conventional project scales at present,the corresponding suggested equipment layout is given in order to shorten the project cycle.
作者
孙钦玺
Sun Qinxi(CNOOC Petrochemical Engineering Co.,Ltd.,Piping Department,Jinan 250101,China)
出处
《山东化工》
2023年第24期187-190,共4页
Shandong Chemical Industry
关键词
煤层气
项目周期
井场
集气站
标准化
coalbed methane
project cycle
well site
gas gathering station
standardization