摘要
以两联三跨连续梁顶升改造施工为工程背景,采用PLC电脑同步控制系统进行顶升施工。通过midas Civil有限元软件建立模型,对桥梁施工顶升过程进行仿真计算,在确保梁体安全的前提下,计算分析得到顶升不均匀位移差控制值。并对顶升过程中的桥梁采取变形、应力、基础沉降、裂缝等监测措施,并制定相应的监测预警值,以期为后续桥梁顶升改造施工提供理论依据。
Based on the engineering background of the jacking construction of two-connected three-span continuous beam,the jacking construction is carried out by using PLC computer synchronous control system.The model is established by midas Civil finite element software,and the whole process of bridge construction and jacking process are simulated and calculated.On the premise of ensuring the safety of the beam body,the control value of uneven displacement difference of jacking is calculated and analyzed.The deformation,stress,foundation settlement,cracks and other monitoring measures are taken for the bridge during the jacking process,and the corresponding monitoring and early warning values are formulated to provide theoretical and technical guidance for the subsequent bridge jacking reconstruction.
作者
徐松
刘聪
XU Song;LIU Cong(NJTech Bridge,Tunnel and Rail Transit Research Institute Co.,Ltd.,Nanjing,Jiangsu 210031,China;Jiangsu Zhongji Engineering Technology Research Co.,Ltd.,Nantong,Jiangsu 226003,China)
出处
《黑龙江交通科技》
2024年第2期79-82,共4页
Communications Science and Technology Heilongjiang
关键词
连续梁
顶升施工
仿真计算
监测
continuous beam
jacking construction
simulation calculation
monitor