摘要
为解决大直径土压盾构在大粒径富水卵石、漂石土地层条件下刀盘刀具磨损严重、刀盘被卡、地表塌陷、渣土喷涌等工程难题,结合都四山地轨道交通项目DSZQ-1标永丰站—蒲阳站区间盾构隧道工程的施工情况,从盾构选型设计、超前地质预警处理、掘进参数选择、渣土改良、螺机防喷涌等方面进行研究,总结出都江堰地区大粒径富水卵石、漂石土地层大直径土压盾构掘进关键技术,为后续工程在此类地层施工提供了借鉴依据。
In order to solve the engineering problems such as the serious wear of the cutter head,the cutter head jammed,the surface collapse and the muck gushing for the large-diameter earth pressure shield under the conditions of large-particle water-rich pebble-boulder soil stratum,combined with the construction situation of the shield tunneling project between Yongfeng Station and Puyang Station in Dusi Mountain Rail Transit Project DSZQ-1,the research is carried out from the aspects of shield selection and design,advanced geological early warning treatment,tunneling parameter selection,muck improvement and screw anti-surge.The key technology of large-diameter earth pressure shield tunneling in Dujiangyan Area with large-particle water-rich pebbles and boulder soil stratum is summarized,which provides a reference basis for the construction of subsequent construction in such stratum.
出处
《城市道桥与防洪》
2024年第2期271-275,I0023,共6页
Urban Roads Bridges & Flood Control
关键词
大直径土压盾构
大粒径卵石
漂石土
地表塌陷
渣土改良
large-diameter earth pressure shield
large-particle pebble
boulder soil
surface collapse
muck improvement