干粉煤气化装置激冷水系统的优化

Optimization of chilled water system in dry pulverized coal gasification plant
下载PDF
导出
摘要 介绍了干粉煤气化装置及其激冷水系统的工艺流程。通过对激冷水系统各支路阻力降的计算分析,发现原激冷水系统工艺流程存在激冷水偏流的可能和风险。通过阻力降计算结果优化了激冷水系统的工艺流程配置,再合理设置调节阀、增设喷淋水管线和冲洗水管线,从根本上解决了激冷水偏流问题。 The process of dry pulverized coal gasification plant and its chilled water system was introduced.In view of the problem of the“flow deflection”in the chilled water system of the semi waste boiler process in the actual operation of the dry pulverized coal gasification plant,the resistance drop of each branch line was calculated and analyzed to find out the reasons of the flow deflection,and the process configuration of the chilled water system was optimized accordingly based on the calculation.By appropriately setting the control valve,adding the water spray line and rinse line,the problem was fundamentally solved.
作者 李叶珺 李燕妮 Li Yejun;Li Yanni(SEDIN Engineering Co.,Ltd.,Taiyuan Shanxi 030032,China)
出处 《煤化工》 CAS 2024年第1期6-8,16,共4页 Coal Chemical Industry
关键词 干粉煤半废锅气化 激冷水系统 偏流 系统优化 调节阀 dry pulverized coal semi waste boiler gasification chilled water system flow deflection problem system optimization control valve
  • 相关文献

参考文献3

二级参考文献5

共引文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部