期刊文献+

汽轮机负荷速降工况下核岛最终功率整定值触发逻辑的优化

Optimization of logic for final reactor power setting value under turbine rapid load drop condition
下载PDF
导出
摘要 在国内核电厂现有的西门子汽轮机控制逻辑中,存在一种特殊工况,该工况下机组未解列,但汽轮机电功率突降,调节系统触发快速降负荷,这种速降负荷的状态未传递给反应堆,反应堆无法触发最终功率整定值,存在反应堆意外停堆的风险。针对以上问题,本文以华龙一号堆机匹配方案为研究对象,分析汽轮机在负荷速降工况下,反应堆最终功率整定值的计算过程,提出一种堆机接口控制逻辑优化方案。经过模型推演,证实优化方案可有效解决现有问题,进一步提升反应堆安全性。 In the current Siemens turbine control logic of nuclear power plant,a special condition is existed,in which the unit does not disconnect with the grid,but the turbine electric power drops suddenly,and the control system triggers rapid load reduction.This state of rapid load reduction is not transmitted to the reactor,and the reactor cannot trigger the final reactor power setting value,there is a risk of accidental reactor trip.In view of the above problem,this thesis takes reactor-turbine interface of HPR1000 as the study case,analyzes the calculation process of the final reactor power setting value under the rapid load drop condition,and puts forward an optimal scheme of the reactor-turbine interface.Through the model simulation,it is proved that the optimized scheme can effectively solve the existing problem and further improve the reactor safety.
作者 张冲 尹刚 刘跃辛 吴官寅 ZHANG Chong;YIN Gang;LIU Yuexin;WU Guanyin(China Nuclear Power Design Co.,Ltd.,Shenzhen of Guangdong Prov.518172,China)
出处 《核科学与工程》 CAS CSCD 北大核心 2023年第6期1414-1418,共5页 Nuclear Science and Engineering
关键词 负荷速降 反应堆最终功率整定值 堆机匹配 Rapid load reducction Final reactor power setting value Reactor-turbine interface
  • 相关文献

参考文献2

二级参考文献3

  • 1王志,等编.GCT系统手册[R].北京:核工业第二研究设计院,1996.
  • 2唐熠远,等编.RRC系统手册[R].成都:中国核动力研究设计院,2000.
  • 3戚屯锋,等编.秦山核电二期模拟图册、逻辑图册[R].浙江:核电秦山联营有限公司,2000.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部