摘要
位于镇江市谏壁发电厂内的两座高210 m的烟囱需进行拆除,受周边环境和正常运行的两台100万机组的影响,振速不能过大。经分析论证,选择两座烟囱相对定向倒塌、空中相碰的方案是影响最小的最优方案,通过选择切口位置、精确定位倒塌方向、开设定向窗、多层次全方位防护等措施,结合对碰模拟分析结果以及现场测试数据等技术手段,最终两座烟囱在空中实现对碰,且周边保护目标安全无恙,此爆破方法为国内首例,对类似工程有一定的借鉴作用。
Two 210-meter high chimneys,sitting in Guodian Jianbi power plant,required demolition blasting with controlled vibration due to surrounding environment and on-going operations of two 1-million kw generator sets.After rounds of analysis and discussion,it was agreed that having the two chimneys directionally collapsed into each other mid-air was the best solution with lowest environmental impacts.By carefully choosing the incision location,precisely designing the collapse direction,setting up directional window,taking multi-level and all-round precautions,along with collision simulation analysis results and on-site testing data,we successfully made the two chimneys collapse into each other mid-air,and targeted surrounding protections were safe and sound.This blasting method was the first of its kind in China,and has certain reference value for similar projects.
作者
张焜琨
张耀良
夏云鹏
张中威
李杰
钱坤
徐阳
陈美常
ZHANG Kun-kun;ZHANG Yao-liang;XIA Yun-peng;ZHANG Zhong-wei;LI Jie;Qian Kun;XU Yang;CHEN Mei-chang(Jiangsu Changjiang Blasting Engineering Co.Ltd.,Zhenjiang 212003,Jiangsu,China;School of Defense Engineering,Army Engineering University of PLA,Nanjing 212000,China;School of Textile Science and Engineering,Jiangnan University,Wuxi 214000,Jiangsu,China;Zhenjiang City Public Security Bureau Public Security Detachment,Zhenjiang 212003,Jiangsu,China)
出处
《工程爆破》
CSCD
北大核心
2024年第1期96-103,共8页
Engineering Blasting
关键词
烟囱
拆除爆破
钢筋混凝土
空中对碰
防护
数值模拟
chimney
demolition blasting
reinforced concrete
mid-air collision
protection