摘要
文中选取了路基工程中有代表性的两类地质,经试桩结果分析得出,采用“四喷四搅+桩顶3 m复搅复喷一次”施工工艺和进、提钻速度控制为300 r/min(0.65 m/min)的施工工艺满足搅拌桩成桩后的各项指标,且经济效益好,在同类工程中具有一定的参考价值。
In this paper,two representative types of geology in roadbed engineering are selected.Through analysis of pile test results,it is concluded that the construction technology of"four injection and four mixing+3 m pile top mixing and spraying once"and the construction technology of driving and lifting drilling speed control of 300 r/min(0.65 m/min)meet all the indicators after mixing pile formation,and the economic benefits are good.It has certain reference value in similar projects.
作者
王琦
Wang Qi(Jiangxi Jiaotou Consulting Group Co.Ltd.,Nanchang,Jiangxi 330006)
出处
《江西建材》
2023年第12期359-361,共3页
Jiangxi Building Materials
关键词
水泥搅拌桩
试桩
施工工艺
试验检测
Cement mixing pile
Test pile
Construction technology
Test detection