莱钢1号1880高炉降料线停炉实践

Practice of Stopping the Material Reduction Line of Laigang No.11880 Blast Furnace
下载PDF
导出
摘要 根据公司生产计划要求,莱钢1号1 880 m^(3)高炉于2023年9月7日12:00开始降料线停炉。9月8日2:08,料线降至预定位置(22.7 m),安全休风停炉。停炉过程安全、顺利、快速,各项参数控制到位。本次降料线总计耗时14 h 8 min、耗风198.4万m^(3)、打水1 834 m^(3),出铁3炉。20:56,开始放残铁。9日00:36,残铁放完,共计放残铁386.25 t。通过精心组织,1 880 m^(3)高炉安全顺利停炉,并创造了停炉降料线用时最短的记录。 According to the company's production plan requirements,Laigang No.11880 m^(3) blast furnace started to shut down at 12:00 pm on September 7,2023.On September 8th at 2:08,the material line was lowered to the predetermined position(22.7 meters),and the furnace was safely shut down.The shutdown process is safe,smooth,and fast,with all parameters controlled in place.The total time taken for this material reduction line is 14 hours and 8 minutes,with a wind consumption of 1.984 million m^(3),draw water 1834 m^(3),cast three furnaces.20:56,start releasing residual iron.At 0:36 on the 9th,the remaining iron was released,totaling 386.25 tons.Through careful organization,1880 m^(3) blast furnace was safely and smoothly shut down,and a record was set for the shortest duration of the shutdown and material reduction line.
作者 王徐波 Wang Xubo(Ironmaking Plant,Shandong Iron and Steel Group Laiwu Branch,Jinan Shandong 271104,China)
出处 《山西冶金》 CAS 2024年第1期124-126,共3页 Shanxi Metallurgy
关键词 高炉 降料线 安全停炉 blast furnace material reduction line safe shutdown
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部