期刊文献+

某厂房项目大跨度预制双T板滑模安装及吊装施工分析

Analysis of Installation and Hoisting Construction of Long-Span Prefabricated Double-T Plate Slip-Form for a Plant Project
下载PDF
导出
摘要 某工程局部区域有夹层结构,双T板无法一次性吊装到位。经对各施工方案的研究、比较和优化,决定采用滑模施工工艺。论文主要研究了大跨度预制双T板安装过程中使用滑模桁架的施工工艺和流程,并对吊装施工的验算复核进行了分析。 Because of the sandwich structure in some areas of a project,the double T plate can not be hoisted in place at one time.After the study,comparison and optimization of each construction scheme,it is decided to adopt the slip-form construction technology.This paper mainly studies the construction technology and flow of slip-form truss used in the installation process of long-span prefabricated double T plate,and analyzes the checking calculation of hoisting construction.
作者 杨磊 马小伟 YANG Lei;MA Xiao-wei(Wuxi Construction Supervision Consulting Co.Ltd.,Wuxi 214000,China)
出处 《工程建设与设计》 2024年第4期193-195,共3页 Construction & Design for Engineering
关键词 大跨度双T板 滑模桁架工艺 吊装施工 large span double T plate slip-form truss technology hoisting construction
  • 相关文献

参考文献4

二级参考文献14

共引文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部