陆水大坝闸墩无损切割拆除施工

Non-Destructive Cutting and Dismantling Construction of Lushui Dam Gate Pier
下载PDF
导出
摘要 除险加固工程中,混凝土结构存在部分拆除的情况,此时必须在保证剩余部分结构不受损坏的基础上完成拆除。针对陆水大坝闸墩的实际情况,采取“绳锯切割、打孔吊装拆除素混凝土+人工破碎钢筋混凝土+气体切割拆除钢结构”的组合施工方案完成闸墩部分拆除,闸墩顶部附属结构全部拆除的任务。该方案在安全文明施工的前提下,圆满地完成了拆除任务,为大坝闸墩恢复施工奠定了基础,保障了枢纽除险加固工程的顺利完成。 During the risk removal and reinforcement project,the concrete structure is partially demolished.At this time,the demolition must be completed while ensuring that the remaining part of the structure is not damaged.In view of the actual situation of the gate pier of Lushui Dam,a combined construction plan of"wire saw cutting,drilling and lifting to remove plain concrete+manual crushing of reinforced concrete+gas cutting to remove steel structure"was adopted to complete the partial demolition of the gate pier,and the top accessory structure of the gate pier All demolition tasks.Under the premise of safe and civilized construction,this plan successfully completed the dismantling task,laid a foundation for the restoration of the dam gate piers,and ensured the smooth completion of the hub risk elimination and reinforcement project.
作者 李丹平 陈祚良 鲍云鹏 LI Danping;CHEN Zuoliang;BAO Yunpeng(Lushui Hydro-complex Administration of Changjiang Water Resources Commission,Chibi,Hubei 437399)
出处 《长江工程职业技术学院学报》 CAS 2024年第1期13-17,共5页 Journal of Changjiang Institute of Technology
关键词 陆水大坝 除险加固 无损切割 拆除 闸墩 Lushui dam danger removal and reinforcement non-destructive cutting demolition gate pier
  • 相关文献

参考文献7

二级参考文献56

共引文献20

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部