考虑资源调配灵活度的项目集缓冲监控

Program buffer monitoring model considering resource allocation flexibility
原文传递
导出
摘要 为提高项目集管理的有效性,提出了一种考虑资源调配灵活度的项目集缓冲监控方法.首先,基于项目集内部和外部不同资源的供应风险和延误风险,确定资源调配弹性风险指标;其次,基于确定的单项目缓冲和项目集缓冲,确定双层缓冲分配方案;最后,在项目集的执行过程中进行缓冲监控,根据缓冲消耗情况对后续缓冲计划进行调整.通过蒙特卡罗模拟实验对案例仿真,与经典的缓冲监控方法对比结果表明,本文方法通过有效的缓冲管理,降低了不确定性影响,提高了项目集工期和成本的综合绩效. To improve the effectiveness of program management,program buffer monitoring method considering resource allocation flexibility was proposed.Firstly,based on the supply risk and delay risk of different resources within and outside the project set,the resource allocation flexibility risk index is determined.Secondly,based on the determined single item buffer and item set buffer,a two-level buffer allocation scheme is determined.Finally,buffer monitoring is performed during the execution of the project set,and subsequent buffer plans are adjusted based on buffer consumption.Through Monte Carlo simulation experiments,a case is simulated.The simulation results show that the proposed method reduces the impact of uncertainty through effective buffer management,and improves the overall performance of project set duration and cost,compared to classic buffer monitoring methods.
作者 张俊光 王熙 韩晴 ZHANG Junguang;WANG Xi;HAN Qing(School of Economics and Management,University of Science and Technology Beijing,Beijing 100083,China)
出处 《系统工程理论与实践》 EI CSSCI CSCD 北大核心 2024年第2期700-713,共14页 Systems Engineering-Theory & Practice
基金 国家自然科学基金(72372008)。
关键词 关键链 项目集管理 资源调配灵活度 缓冲监控 critical chain program management flexibility of resource allocation buffer monitoring
  • 相关文献

参考文献24

二级参考文献187

共引文献773

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部